Unit Banner

Statistical Information

  • Construction start date: October 22, 2007
  • Expected completion date: Winter 2009
  • Construction Cost: $46,590,000
  • Gross square footage: 139,569
  • Assignable square footage: 101,403
  • Percent (%) of project complete: 26%

Progress of Major Construction Activities

  • Welding of brace frame steel still in progress
  • Placement of reinforcing steel for foundations for next pour in progress
  • Export of dirt stockpile started this week

Key/Critical Issues Currently Pending

  • None at this time

Upcoming Interruptions

  • Major utilities interruption will occur during utility tunnel work.  Contractor coordinating with University Physical Plant, proposed for summer 2008.

© 2007 California State University, Dominguez Hills, 1000 E. Victoria Street, Carson, CA 90747 (310)243-3696
If any of the material is in violation of a copyright, please contact copyright@csudh.edu.
Last updated Monday, May 05, 2008, by J. McTaggart
Disclaimer |
Browser Support