Statistical Information
- Construction start date: October 22, 2007
- Expected completion date: Winter 2009
- Construction Cost: $46,590,000
- Gross square footage: 139,569
- Assignable square footage: 101,403
- Percent (%) of project complete: 26%
Progress of Major Construction Activities
- Welding of brace frame steel still in progress
- Placement of reinforcing steel for foundations for next pour in progress
-
Export of dirt stockpile started this week
Key/Critical Issues Currently Pending
Upcoming Interruptions
- Major utilities interruption will occur during utility tunnel work.
Contractor coordinating with University Physical Plant, proposed for summer
2008.