Project Status Report – Presented to the Academic Senate

March 6, 2002

 

 

We have a number of projects underway on campus.  The following is the status of these projects and their expected completion dates:

 

James L. Welch Hall                              Project Completion Date: October/November 2002

This new building is the first state-funded facility to be constructed at California State University, Dominguez Hills since the late 1970s.  It is a four-story building with approximately 115,000 assignable square feet that will house the School of Health, Student Services, the Computer Center, and Administration.  The project also includes classroom space to serve over 1,000 full time equivalent students. The building is currently at 65% completion.  Welch Hall will greatly relieve our significant space issues on campus.  We have a website that provides information about Welch Hall as well as construction progress pictures.  http://www.csudh.edu/admfin/FP/ITphotos.htm

 

 

National Sports Training Center                                   Project Completion Date: June 2003

With an expected opening of the venue in June 2003, the construction will move at a very fast pace.  The fencing around the project area is up.  The velodrome is being demolished this week. The northwest entrance of parking lot 6 (near the velodrome site) will be closed beginning Monday, March 11 for about 3 months. A new parking lot will be constructed between parking lot 6 and the Extended Education building. This new parking lot will be part of the campus parking inventory in place of parking lot 7.  The contractor, PCL, will be working out of the old Child Development Center/Infant Toddler Center.  Stan Hebert will serve as the primary contact for questions or concerns related to the construction of this project.  Randy Sharp will serve as Stan's alternate.  Their phone numbers and e-mails are: Stan Hebert (310) 243-3874, shebert@csudh.edu; Randy Sharp (310) 243-2163, rsharp@csudh.edu.  In order to document the construction of this project, a webcam is being proposed on top of ERC.  A website has been established for this project at:   http://www.csudh.edu/admfin/proposal/proposal.htm

 

 

 

Smart (Mediated) Classrooms                                                                                On –going

Since August 2001, 16 classrooms have been renovated to smart (mediated) classrooms.  The 16 classrooms that have been renovated to date are: SBS A-144, SBS B-109, SBS B-115, SBS B-131, SBS B-215, SBS D-125, SBS F-125, SCC 11-305, NSM B-242, NSM B-252, NSM C-221, LCH A-103, LCH A-219, LCH A-224, LCH A-228, LCH A-324. All of the smart (mediated) classrooms include a ceiling-mounted projector, projection screen, PC, VCR, a pair of wall-mounted speakers and the central control unit (the podium). The PC is connected to our network and to the Internet.  MS Office (Word, Excel, PowerPoint, and Access) is installed on the PC’s.  The VCR plays VHS video tapes, and the PC plays the standard data and music CD’s.  All of the features (sound volume, switching from PC to VCR, etc.) are controlled on the podium, the central control unit.  In addition, there are data and sound connectors on the podium which are designed for the quick connection of a laptop to the “smart” system.  This allows those professors who prefer to use their own laptops instead of the built-in PC in the podium to present their class materials.

Funding is still available for the renovation of 8 to 10 additional classrooms.  The remaining 8 to 10 classrooms, to be determined by Academic Affairs, are scheduled for completion by Fall 2002.  Additional information regarding Smart Classrooms are included in the attached report that was submitted to the University Budget Committee in February 2002.

 

Telecommunications Infrastructure Project                Project Completion Date: June 2003

This project will upgrade critical infrastructure components of the telecommunications system that are essential to support changes in instructional technology that will help us meet the need for expanded telecommunications. 

 

 

We ask for your patience as most offices, classrooms, and labs will be impacted on some level or another (new or upgraded voice and data jacks). The contractor has mobilized in the fenced-in area up on the plateau just east of the new East Academic Complex (EAC). The first buildings to be impacted will be Student Health and very limited areas on the first floor of ERC. There will be Building Captains assigned to facilitate user inquiries. The Building Captains will attend periodic project meetings and make sure occupants are informed when the contractor is coming into their areas. Most of the new fiber will be installed in the campus tunnel system.  There will be some trenching around the campus in areas not accessible by the campus tunnel system. 

 

Emergency Phones                                                       Project Completion Date: April 2002

Current emergency telephones placed throughout campus do not meet ADA requirements for accessibility and use.  Additional issues include: difficult operation due to their configuration, inadequate phone coverage throughout campus areas and sub-par performance.  Due to these safety concerns, the campus is replacing existing phones and adding seven new phone locations.  Of the 36 existing phones, 29 are slated for replacement, including new elevator phones.   The remaining locations have been upgraded to the new specification.  The seven new locations were chosen by Public Safety and the Office of Risk Management/Environmental Health and Occupational Safety.  There will be some trenching around the campus in areas where electrical conduit and telephone lines are needed for this project 

 

Exterior Lighting Project                                              Project Completion Date: April 2002

The purpose of this project is to improve exterior lighting along major walkways, stairwells and open areas campus wide.  There will be some trenching around the campus in areas where electrical conduit is needed. 

 

School of Education Building Addition                          Project Completion Date: June 2002

This project expands the School of Education Building by approximately 1,200 square feet.  This space will serve as a classroom and storage area.  The expansion is being built on the old loading dock on the southeast corner of the building. 

 

NSM Patio Landscape                                                    Project Completion Date: April 2002

This project renovates the outside patio areas on the north side of the three-story portion of the NSM building.

 

East Academic Complex (EAC) Landscape                 Project Completion Date: March 2002

This project provides the landscape portion of the newest temporary space project that has been completed east of SBS.

 

 

Swimming Pool Filter System Repair                        Project Completion Date: March  2002                       

The pool is currently shut down to replace the surge pit and filter system.  This will take about three weeks.  We have tried to avoid shutting the pool down during the semester but have run out of options.  The testing of the water does not reveal any harmful substance, it is just not aesthetically pleasing.

 

New Security Door Locks                                  Initial Project Completion Date: April  2002

The initial phase of this project installs over 60 new security locks on doors accessing smart classrooms and other high risk areas.  Additional security locks will be installed as new funding is provided.

 

 

Upcoming projects:

 

Walkway Replacement (Area between SBS and EAC)                       Timeline: Spring Break

 

Paint Exterior of NSM                                            Start date: End of Spring 2002 Semester

 

Paint Exterior of LCH                                             Start date: End of Spring 2002 Semester

 

Proposed Removal of Falkenstein (Log) Sculpture                          Timeline: Under review

In June 2000, a 10 year old boy fell off of the Falkenstein Sculpture.  Since that time, the sculpture has been fenced off for health and safety reasons as alternatives have been evaluated.  A safety review of the sculpture has found that it is unstable primarily due to termite infestation.  Renovation of the sculpture would require the replacement of all of the logs.  Even with renovation, the sculpture is still a safety issue because unfortunately it is often climbed on and there is a risk of someone falling off and getting hurt.  We have been in contact with the Falkenstein Foundation, the Long Beach Museum of Art and the Oakland Museum of California.  All of these organizations have indicated that they are not able to receive this work as a gift.  As such, the current proposal that will be taken to the Exterior Artwork Committee will be to have it removed.

 

New Child Development Center/                                         Start date: Fall 2002 Semester           

Infant Toddler Center.

As part of the agreement with the developer of the National Sports Training Center, the developer has agreed to provide $550,000 for a permanent replacement facility for the Child Development Center and Infant Toddler Center.  A possible location and design will be discussed with the Campus Physical Master Planning Committee over the next couple of months.