Project Scope
Bringing a 21st Century Network Infrastructure to CSUDH
The project provides:
- Additional pathways to distribute infrastructure of
copper and fiber cables through out the campus
- Additional copper and fiber cables as a backbone to
connect campus buildings
- Relocation of the campus phone switch and data
switch/router to a larger, enhanced network control center
- New and/or improved telecommunications rooms in all
buildings, including electrical and mechanical improvements as well as
architectural
- Pathways to facilitate the installation of interior
cabling in most campus buildings
- Replacement of infrastructure for voice and data with
CAT5e certified cable, new outlets, and faceplates
- Additional cable trays in the tunnels
- Additional conduits to the south of the ERC building
along the western side of the athletics buildings
- Additional conduits to the north of LaCorte Hall to the
grass area north of the student union
- New network electronics. The equipment supplier is
CISCO and the project integrator is SBC Datacomm. All equipment will be
capable of 10/100 Mb/sec switched Ethernet
- Two data jacks in every classroom/lab in most campus
buildings (see list of included buildings)
- Two data and one phone jack in every office in most
campus buildings (see list of included buildings).
The contractor is expected to work during the night after
10 p.m. in any building where a disruption to students and faculty is possible.
Work in these areas will stop at 6 a.m.
This project will take approximately 16 months to complete.
The work is passed and sequenced in order to minimize disruption to campus
activities.
|