Phases and Timelines
Bringing a 21st Century Network Infrastructure to CSUDH
Length of Project: 485 calendar days from Notice to
Proceed date [Feb.11]
Stage 1 - Construction and Wiring
| Part
1 - Exterior Construction [126 days - will overlap Part 2] |
|
|
|
|
|
Phase A |
35 days |
Cable tray in tunnel from ERC
west to area north of LCH; cable tray from ERC into LCH. |
|
Concurrent with Phase B. |
|
Phase B |
42 days |
New conduit from tunnel north of LCH to LSU and north into SHC basement. Trenching along west side of mall. |
|
|
|
|
|
Phase C |
42 days |
Cable tray in tunnel from ERC east to NSM and to SB north of Vault 100. |
|
Concurrent with Phase D |
|
Phase D |
28 days |
Conduit from new manhole on west side of mall near SHC to existing manhole near SCC 1 Computer Ctr. |
|
|
|
|
|
Phase E |
42 days |
Conduit from ERC west; south past Field House, Hughes Athletic Center, east to new manhole near CAMS |
|
|
|
|
| Part
2 - Interior Building Construction |
|
|
|
|
|
Phase 1 |
70 days |
Preparation and construction of NCC/MDF in ERC
C112/G152 |
|
Interior pathways, outlet wiring of pilot building -
SHC [Bldg 25] |
|
|
|
|
|
Phase 2 |
42 days |
Preparation for and move of telephone switch to new
NCC/MDF |
|
Scheduled for May 27, 2002 |
|
|
|
|
|
Phase 3 |
126 days |
Interior pathways, outlet wiring, data comm rooms in UT, LCH, ERC 1st floor only |
|
|
|
|
|
Phase 4 |
91 days |
Interior pathways, outlet wiring, data comm rooms in Gym, FH, Hughes Athletic Center |
|
|
|
|
|
Phase 5 |
154 days |
Interior pathways, outlet wiring, data comm rooms in NSM, SBS, SOE, PP, CP |
|
|
|
|
|
Phase 6 |
84 days |
Interior pathways, outlet wiring, data comm rooms in SCC 6, 7,8,9,10,11 |
|
|
|
|
|
Phase 7 |
84 days |
Interior pathways, outlet wiring, data comm rooms in SCC 1,2,3,4,5,12 |
|
|
|
|
Stage 2 - Installation, Configuration of Network Hardware; Cutover
| Concurrent with
Stage 1, Part 2, Phases 1 -7 above. Cutover of data and telephone connections to new infrastructure; installation of new
patch cords |
|