Phases and Timelines

Bringing a 21st Century Network Infrastructure to CSUDH

Length of Project: 485 calendar days from Notice to Proceed date [Feb.11]

Stage 1 - Construction and Wiring

Part 1 - Exterior Construction [126 days - will overlap Part 2]
Phase A 35 days Cable tray in tunnel from ERC  west to area north of LCH; cable tray from ERC into LCH.
Concurrent with Phase B.
Phase B 42 days New conduit from tunnel north of LCH to LSU and north into SHC basement. Trenching along west side of mall.
Phase C 42 days Cable tray in tunnel from ERC east to NSM and to SB north of Vault 100.
Concurrent with Phase D
Phase D 28 days Conduit from new manhole on west side of mall near SHC to existing manhole near SCC 1 Computer Ctr.
Phase E 42 days Conduit from ERC west; south past Field House, Hughes Athletic Center, east to new manhole near CAMS
Part 2 - Interior Building Construction
Phase 1 70 days Preparation and construction of NCC/MDF in ERC C112/G152
Interior pathways, outlet wiring of pilot building - SHC [Bldg 25]
Phase 2 42 days Preparation for and move of telephone switch to new NCC/MDF
Scheduled for May 27, 2002
Phase 3 126 days Interior pathways, outlet wiring, data comm rooms in UT, LCH, ERC 1st floor only
Phase 4 91 days Interior pathways, outlet wiring, data comm rooms in Gym, FH, Hughes Athletic Center
Phase 5 154 days Interior pathways, outlet wiring, data comm rooms in NSM, SBS, SOE, PP, CP
Phase 6 84 days Interior pathways, outlet wiring, data comm rooms in SCC 6, 7,8,9,10,11
Phase 7 84 days Interior pathways, outlet wiring, data comm rooms in SCC 1,2,3,4,5,12

Stage 2 - Installation, Configuration of Network Hardware; Cutover

Concurrent with Stage 1, Part 2, Phases 1 -7 above. Cutover of data and telephone connections to new infrastructure; installation of new patch cords