Residence Hall - Phase III

BOT ApprovedOpenedCostFund SourceSizeGeneral ContractorArchitectCertification
Mar 2018Fall 2021$55.87 MillionHousing Enterprise97,000 GSFPCL ConstructionSteinberg HartLEED Silver

Project Description

The Student Housing Phase III Project is a 506 bed complex of dormitory-style student housing. The new student housing complex includes a 4-Story Residence Building and a 1-Story Commons Building. The Residence Building includes double, triple and quadruple bedrooms, shared restrooms, private bedrooms for 11 Resident Advisors, a laundry room, study rooms, several small and large lounges and a two-bedroom apartment for the Residential Coordinator. The Commons Building includes administrative offices, kitchenettes and common areas, lounge and multi-purpose (active) space, mail/package delivery room, vending area, a convenience store, common restrooms, study room (passive) for small groups and other miscellaneous support spaces such as trash/recycling pickup.  

The project is located south of International Avenue, west of Birchknoll Drive, and north of the existing main central plant (Building I.D. No. 87) / Unity Drive.  

Site improvements include landscaping, exterior lighting, building and wayfinding signage, visitor/temporary parking, pick-up/drop-off zones, fire lanes, access for trash collection, an outdoor semi-shaded seating area, semi-shaded bicycle racks, a barbeque/picnic area.


Questions

Email Facilities Planning, Design & Construction at fpdc@csudh.edu, or call us at (310) 243-3826.