BOT Approved | Est. Open | Cost | Fund Source | Size | General Contractor | Architect |
Jan 2024 | Fall 2025 | $31 Million | $20M State Grant $2M SCE Credits | 13,375 GSF | C.W. Driver | P2S Engineering / Digital Energy Inc. |
CSUDH continues to transform. Construction begins Monday, November 13, 2023, and mobilization is underway to prepare the site for the construction of the New Electrical Switchyard Project and New Heat Pumps at the Central Plant Facility.
A construction fence will be completed by Friday, November 10, 2023, around the construction site (orange) and construction trailers will be located across Birchknoll Drive on the gravel lot (purple).
Pedestrian pathways from Parking Lots 1 & 2 to Parking Lot 7, Science & Innovation, SAC 2 and 3, and Classroom Village are rerouted along Student Housing Phase I and II walkways. Please see the map below for additional details.
In addition, a new pedestrian sidewalk will be constructed alongside the west side of Birchknoll Drive from International Ave. to Unity Drive. For minimal disruption to the campus operations, this work is projected to begin in summer of 2024.
Please be aware of construction activities along Birchknoll Drive and always watch for construction traffic. Do not enter construction sites. The main driving route to the jobsite for construction deliveries will be from the Central Avenue campus gate, with access to campus from International Drive.
Pedestrian access (red dotted lines) around the project site will remain open and available during the construction phase with minor exceptions. Signage will be strategically placed around the construction zone.
If you have any questions or concerns regarding this project, please contact Facilities Planning, Design and Construction (FPDC) Jose Gonzalez at (310) 243-1073.